On 20 July 2020, the Australian Renewable Energy Agency (ARENA) announced that seven companies have been shortlisted to advance to the full application stage of ARENA’s Renewable Hydrogen Deployment Funding Round (Funding Round).

ARENA aims to provide funding of up to $70 million to support at least two projects that involve the deployment of a new-build electrolyser as part of either a brownfield or greenfield project for the production of renewable hydrogen. The Funding Round is an effort to support the Australian Government’s aim of building a world-class hydrogen industry.  This includes seeking to fast track the achievement of the Australian Government’s goal of producing renewables-based hydrogen for less than $2 per kilogram, also described as “H2 under $2”.

The seven shortlisted applicants (selected from a field of 36) are:

  • APT Management Services Pty Limited;
  • ATCO Australia Pty Ltd;
  • Australian Gas Networks Limited;
  • BHP Billiton Nickel West Pty Ltd;
  • Engie Renewables Australia Pty Ltd;
  • Macquarie Corporate Holdings Pty Limited; and
  • Woodside Energy Ltd.

According to ARENA, all shortlisted applicants have well developed projects that involve deploying 10MW or larger electrolysers, made up of various end uses including transport, gas injection, renewable ammonia production, power and industrial use. Four of the projects are based in Western Australia, and one each in Queensland, Tasmania and Victoria.

The projects seek $200 million in grant funding in total towards a collective project value of almost $500 million.

All applicants may also be considered for financing from the Clean Energy Finance Corporation under the corporation’s $300 million Advancing Hydrogen Fund.

Applicants must submit their full application by 20 January 2021. Successful applicants will be issued a non-binding offer to negotiate a Funding Agreement (expected to occur in mid-2021). A recipient of an offer must provide ARENA with a bid bond of $500,000 within 20 business days of the date of the offer.

Financial close is expected to occur by late 2021 and construction is expected to commence in 2022. The selected hydrogen projects are speculated to be among some of the largest electrolysers in the world.

Access the media release by ARENA here and the blog post by ARENAWIRE here.

Important Disclaimer: The material contained in this article is comment of a general nature only and is not and nor is it intended to be advice on any specific professional matter. In that the effectiveness or accuracy of any professional advice depends upon the particular circumstances of each case, neither the firm nor any individual author accepts any responsibility whatsoever for any acts or omissions resulting from reliance upon the content of any articles. Before acting on the basis of any material contained in this publication, we recommend that you consult your professional adviser. Liability limited by a scheme approved under Professional Standards Legislation (Australia-wide except in Tasmania).

Related insights Read more insight

Paying with scrip? Key considerations for junior ASX-listed mining companies

The past year has undoubtedly been challenging for companies in the lithium, rare earth and critical minerals sectors. To provide some context, lithium carbonate, lithium hydroxide and spodumene...

More
Tailings dams and the energy transition – how are they connected?

The Samarco and Brumadinho tailings dam disasters in Brazil were (in no small part) the impetus for the creation of the ‘Global Industry Standard on Tailings Management’. The Standard is now being...

More
JWS advises Bowen Coking Coal Limited (ASX: BCB) on sale of minority stake in Broadmeadow East mine

JWS has advised ASX-listed Bowen Coking Coal Limited (ASX: BCB) on the sale of a 10 per cent stake in the Broadmeadow East mine to Formosa for A$13 million plus royalties.

More